Following
is the pour card for concrete work which can be used on construction sites.
Please note this is for reference only and actual concrete pour card depends on
your construction site.
We at
royalcivilz.blogspot.com are helping all civil engineers who are working on
construction projects.
1.
Standard Sieves
Sieve diameter: 200 mm
Mesh size – 0.075 mm, 0.1 mm, 0.25 mm, 0.5 mm, 1 mm, 2 mm, 5 mm, 10 mm, and 20
mm, with pan and lid.
2. Digital Sieve Shaker
3. Balance & scale
Capacity:
(1) 200 g/0.001 g
(2) 3000g/0.01 g;
(3) 20 kg/1 g
4. Digital Display Constant Temperature Convection Oven
5. Standard Proctor Compactor & Modified Proctor Compactor
6. 150KN Universal Electric Extruder
7. Sand Replacement Test Sets (Galvanized Steel)
8. Sand Cone Test Sets
9. Digital liquid plastic limit
united device
10. Disc type liquid limit device
(Casagrande Method)
11. Plastic Limit Test Sets
12. Shrinkage Limit Test Set
13. Falling Head Soil Permeability Apparatus
14. Constant Head Permeability Apparatus
15. Electric Strain Unconfined Compression Tester
16. Triplex Consolidation Apparatus
17. Duodenary Direct Shear Pre-pressing Apparatus
18. Electric Strain Direct Shear Testing Apparatus
19. Four-bladed Vane Shear Testing Apparatus
20. Consolidation and Permeability United Apparatus
21. Triaxial Test Set
22. CBR Machine
23. Field CBR Test Set
24. Field Loading Plate Test Apparatus
25. Relative Density Apparatus
26. Digital Display Hydraulic Compression Testing Machine
27. Resilience Modulus Test Apparatus
28. Portable Mixer (Universal)
29. Large pulverizing machine
30. Capillary Water Rise Height Tester
31. Expansion Apparatus
32. Shrinkage Testing Meter
33. Free Swelling Rate Meter
34. Speedy Moisture Test Sets
35. Natural Slope Test Sets
36. Stainless steel cutting ring
37. Aluminum can
38. Enamel tray
39. Wire Saw
40. Scraper, spatula, and Shovel or Scoop
41. Graduated flask and stirrer
42. Thermometers
43. Hydrometer
44. Desiccators
45. Caliper
46. Soil Pycnometer
47. Mortar and Pestle
48. Soil sampling device
49. Vacuum Saturator Apparatus
50. Linear Shrinkage Mould
Clear
cover to main reinforcement in
Footings : 50 mm
Raft foundation Top : 50 mm
Raft foundation Bottom/ sides : 75 mm
Strap Beam : 50 mm
Grade Slab : 20 mm
Column : 40 mm (d>12mm) 25 mm (d= 12mm)
Shear Wall : 25 mm
Beams : 25 mm
Slabs : 15 mm or not less than diameter of the bar.
Flat Slab : 20 mm
Staircase : 15 mm
Retaining Wall on Earth : 20/ 25 mm
Water retaining structures : 20 / 30 mm
Sunshade (Chajja) : 25 mm
Hook for
stirrups is 9D for one side
No. of
stirrups = (clear span/Spanning) + 1
For
Cantilever anchorage length for main steel is 69D
“L” for
column main rod in footing is minimum of 300mm
Chairs of
minimum 12 mm diameter bars should be used.
Minimum
diameter of dowel bars should be 12 mm
Lap
slices should not be used for bar larger than 36 mm.
In steel
reinforcement binding wire required is 8 kg per MT.
Lapping
is not allowed for the bars having diameters more than 36 mm.
Minimum
number of bars for a square column are 4 and for circular column are 6.
Longitudinal
reinforcement should not be less than 0.8% and more than 6% of gross C/S.
Weight of
rod per meter length = d2/162 where d is the diameter in mm
All
reinforcement shall be free from mill scales, loose rust & coats of paints,
oil or any other substances.
Main bars
in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the
distributors not less than 8 mm and not more than 1/8 of slab thickness.
In case
of spacing of bars
Provide the diameter of the bar, if the diameter of the bar are equal.
Provide the diameter of the larger bar, if the diameter are unequal.
5mm more than the nominal maximum size of the coarse aggregate.
Minimum
thickness of slab is 125 mm.
Water
absorption should not be more than 15 %.
Dimension
tolerance for cubes + – 2 mm.
Compressive
strength of Bricks is 3.5 N /mm2
Maximum
Free fall of concrete allowed is 1.50 m.
In soil
filling as per IS code for every 100 sqm 3 sample for core cutting test should
be taken.
Electrical
conduits shall not run in column
Earth
work excavation for basement above 3 m should be stepped form
Any back
filling shall be compacted 95% of dry density at the optimum moisture content
and in layers not more than 200mm for filling above structure and 300 mm for no
structure
F soling
is specified the soling stones shall be laid at 45° to 60° inclination (and not
vertical) with interstices filled with sand or moorum.
A set of
cube tests shall be carried out for each 30 cum of concrete / each levels of
casting / each batch
of cement.
Water
cement ratio for different grades of concrete shall not exceed 0.45 for M20 and
above and 0.50 For M10 / M15 contractor
For
concrete grades M20 and above approved admixture shall be used as per mix
design requirements.
Cement
shall be stored in dry places on a raised platform about 200mm above floor
level and 300mm away from walls. Bags to be stacked not more than 10 bags high
in such a manner that it is adequately protected from moisture and
contamination.
Samples
from fresh concrete shall be taken and at least a set of 6 cubes of 150mm shall
be prepared and
cured. 3 Cubes each at 7 days and 28 days shall be tested for compressive
strength. The test results
should be submitted to engineer for approval. If results are unsatisfactory
necessary action/rectification/remedial measures has to be exercised.
Water
used for both mixing and curing shall be clean and free from injurious amounts
of oils, acids, alkalies, salts, sugar and organic materials or other
substances that may be deleterious to concrete or steel. The ph shall be
generally between 6 and 8.
Cement
shall be tested for its setting.
1. The initial setting time shall not be less than 30 minutes.
2. The final setting time shall not be more than 10 hours.
Slump IS
456
Lightly reinforced 25 – 75 mm
Heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm (For Tremie no need of vibrator)
Curing
Days Required
Super Sulphate cement : 7 days
Ordinary Portland cement OPC : 10 days
Minerals and Admixture added cement : 14 days
Cube
Samples
1 – 5 M3 : 1 No.
6 – 15 M3 : 2 No’s
16 – 30 M3 : 3 No’s
31 – 50 M3 : 4 No’s
Above 50 M3 : 4 + 1 No of addition sample for each 50 M3.
check
list which is of great use to all civil engineers.
Accuracy of
measuring equipment in batching plant.
Cement : + – 2%
Aggregate : + – 3%
Admixture : + – 3%
Water : + – 3%
Mixing time : 2 minutes for one mixing. (Mixing which is being done on site)
Tolerance in Form
work
In C/S for columns & Beams deviation is = + 12mm more (or) – 6mm less in
size
In footing plan = + 50 mm more (or) – 12 mm less size
In depth = + – 0.05 D (specified thickness).
Tolerance in
Reinforcement
For effective depth D < = 200mm = +- 10mm
For effective depth D > 200mm = +- 15mm
For Cover to reinforcement = + 10mm
Maximum freefall of concrete = 1.50 m height.
Tolerance on
diameter in length
0-25mm = +- 0.5 %
25-35mm = +- 0.6 %
35-50mm = +- 0.8 %
Tolerance on weight
per metre
0-10mm = +- 7%
10-16mm = +- 5%
16 and above = +- 3%
Tolerance for
cutting Length
A) When the specified length is not given = + 75mm (or) – 25 mm
B) When the minimum length is specified = + 50 mm (or) – 0 mm
Sieve diameter: 200 mm
Mesh size – 0.075 mm, 0.1 mm, 0.25 mm, 0.5 mm, 1 mm, 2 mm, 5 mm, 10 mm, and 20 mm, with pan and lid.
2. Digital Sieve Shaker
3. Balance & scale
Capacity:
(1) 200 g/0.001 g
(2) 3000g/0.01 g;
(3) 20 kg/1 g
4. Digital Display Constant Temperature Convection Oven
5. Standard Proctor Compactor & Modified Proctor Compactor
6. 150KN Universal Electric Extruder
7. Sand Replacement Test Sets (Galvanized Steel)
8. Sand Cone Test Sets
11. Plastic Limit Test Sets
12. Shrinkage Limit Test Set
13. Falling Head Soil Permeability Apparatus
14. Constant Head Permeability Apparatus
15. Electric Strain Unconfined Compression Tester
16. Triplex Consolidation Apparatus
17. Duodenary Direct Shear Pre-pressing Apparatus
18. Electric Strain Direct Shear Testing Apparatus
19. Four-bladed Vane Shear Testing Apparatus
20. Consolidation and Permeability United Apparatus
21. Triaxial Test Set
22. CBR Machine
23. Field CBR Test Set
24. Field Loading Plate Test Apparatus
25. Relative Density Apparatus
26. Digital Display Hydraulic Compression Testing Machine
27. Resilience Modulus Test Apparatus
28. Portable Mixer (Universal)
29. Large pulverizing machine
30. Capillary Water Rise Height Tester
31. Expansion Apparatus
32. Shrinkage Testing Meter
33. Free Swelling Rate Meter
34. Speedy Moisture Test Sets
35. Natural Slope Test Sets
36. Stainless steel cutting ring
37. Aluminum can
38. Enamel tray
39. Wire Saw
40. Scraper, spatula, and Shovel or Scoop
41. Graduated flask and stirrer
42. Thermometers
43. Hydrometer
44. Desiccators
45. Caliper
46. Soil Pycnometer
47. Mortar and Pestle
48. Soil sampling device
49. Vacuum Saturator Apparatus
50. Linear Shrinkage Mould
Footings : 50 mm
Raft foundation Top : 50 mm
Raft foundation Bottom/ sides : 75 mm
Strap Beam : 50 mm
Grade Slab : 20 mm
Column : 40 mm (d>12mm) 25 mm (d= 12mm)
Shear Wall : 25 mm
Beams : 25 mm
Slabs : 15 mm or not less than diameter of the bar.
Flat Slab : 20 mm
Staircase : 15 mm
Retaining Wall on Earth : 20/ 25 mm
Water retaining structures : 20 / 30 mm
Sunshade (Chajja) : 25 mm
Provide the diameter of the bar, if the diameter of the bar are equal.
Provide the diameter of the larger bar, if the diameter are unequal.
5mm more than the nominal maximum size of the coarse aggregate.
of cement.
cured. 3 Cubes each at 7 days and 28 days shall be tested for compressive strength. The test results
should be submitted to engineer for approval. If results are unsatisfactory necessary action/rectification/remedial measures has to be exercised.
1. The initial setting time shall not be less than 30 minutes.
2. The final setting time shall not be more than 10 hours.
Lightly reinforced 25 – 75 mm
Heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm (For Tremie no need of vibrator)
Super Sulphate cement : 7 days
Ordinary Portland cement OPC : 10 days
Minerals and Admixture added cement : 14 days
1 – 5 M3 : 1 No.
6 – 15 M3 : 2 No’s
16 – 30 M3 : 3 No’s
31 – 50 M3 : 4 No’s
Above 50 M3 : 4 + 1 No of addition sample for each 50 M3.
Cement : + – 2%
Aggregate : + – 3%
Admixture : + – 3%
Water : + – 3%
Mixing time : 2 minutes for one mixing. (Mixing which is being done on site)
In C/S for columns & Beams deviation is = + 12mm more (or) – 6mm less in size
In footing plan = + 50 mm more (or) – 12 mm less size
In depth = + – 0.05 D (specified thickness).
For effective depth D < = 200mm = +- 10mm
For effective depth D > 200mm = +- 15mm
For Cover to reinforcement = + 10mm
Maximum freefall of concrete = 1.50 m height.
0-25mm = +- 0.5 %
25-35mm = +- 0.6 %
35-50mm = +- 0.8 %
0-10mm = +- 7%
10-16mm = +- 5%
16 and above = +- 3%
A) When the specified length is not given = + 75mm (or) – 25 mm
B) When the minimum length is specified = + 50 mm (or) – 0 mm